● A non-critical path activity is completed in half the time. Then,
A The critical path is also reduced.
B The slack in the path containing this activity will increase.
C The total cost for this activity has decreased.
D Manpower from this activity can be assigned to other activities.
E All of the above.
第1题
A non-critical path activity is completed in half the time. Then,
A.The critical path is also reduced.
B.The slack in the path containing this activity will increase.
C.The total cost for this activity has decreased.
D.Manpower from this activity can be assigned to other activities.
E.All of the above.
第2题
88 A non-critical path activity is completed in half the time. Then,
A. The critical path is also reduced.
B. The slack in the path containing this activity will increase.
C. The total cost for this activity has decreased.
D. Manpower from this activity can be assigned to other activities.
E. All of the above
第3题
170 A non-critical path activity is completed in half the time. Then,
A. The critical path is also reduced.
B. The slack in the path containing this activity will increase.
C. The total cost for this activity has decreased.
D. Manpower from this activity can be assigned to other activities.
E. All of the above.
第4题
A. Replacing the CAT5 cables with CAT6 cables
B. Replacing traditional racks with water cooled racks
C. Turning off non-critical application servers during non-business hours
D. Taking the second power supply out of non-critical servers
第5题
A. Deploy the service pack to a single department within the corporation.
B. Upgrade the system with requirements for that service pack.
C. Deploy the service pack to a non-critical application server.
D. Submit a change control for the service pack deployment.
第6题
82 Once the logic of a network is laid out, the project manager will conduct a forward pass and backward pass through the network. This will provide information on the _____ and identification of the _____ . A. Slack for each activity, critical path.
B. Slack for each activity, high risk activities.
C. Manpower shortages, high risk activities.
D. High risk activities, non-critical paths.
E. Manpower availability, contingency plans
第7题
A.Slack for each activity, critical path.
B.Slack for each activity, high risk activities.
C.Manpower shortages, high risk activities.
D.High risk activities, non-critical paths.
E.Manpower availability, contingency plans.
第8题
164 Once the logic of a network is laid out, the project manager will conduct a forward pass and backward pass through the network. This will provide information on the _____ and identification of the _____ .
A. Slack for each activity, critical path.
B. Slack for each activity, high risk activities.
C. Manpower shortages, high risk activities.
D. High risk activities, non-critical paths.
E. Manpower availability, contingency plans