Which of the following impacts the critical path?
A.Changing the task duration.
B.Reduce the free float of an activity.
C.Executing a backward pass
D.A or B
E.None of the above.
第4题
● Which of the following impacts the critical path?
A Changing the task duration.
B Reduce the free float of an activity.
C Executing a backward pass
D A or B
E None of the above.
第5题
160 Which of the following impacts the critical path?
A. Changing the task duration.
B. Reduce the free float of an activity.
C. Executing a backward pass
D. A or B
E. None of the above
第6题
42 Which of the following impacts the critical path?
A. Changing the task duration.
B. Reduce the free float of an activity.
C. Executing a backward pass
D. A or B
E. None of the above
第8题
A.hand … in
B.live … on
C.turn … on
D.pass … on
第9题
Delegation may
A . defer the decision on type of approach to be used.
B . be interpreted as passive and uncaring
C . tend to emphasize the task over the people involved.
D . be frequently utilized by a project manager.
E . All of the above.