题目
The project is designed to provide young people ________ work.
A、for
B、with
C、to
D、as
第1题
There is nothing in this world constant but inconstancy.--SWIFT
Project after project designs a set of algorithms and then plunges into construction of customer-deliverable software on a schedule that demands delivery of the first thing built.
In most projects,the first system built is (71) usable,It may be too slow,too big,awkward to use,or all three.There is no (72) but to start again,smarting but smarter,and build a redesigned version in which these problems are solved.The discard and (73) may be done in one lump,or it may be done piece-by-piece.But all large-system experience shows that it will be done.Where a new system concept or new technology is used,one has to build a system to throw away,for even the best planning is not so omniscient(全知的)as to get it right the first time.
The management question,therefore ,is not whether to build a pilot system and throw it away.You will do that.The only question is whether to plan in advance to build a (74),or to promise to deliver the throwaway to customers.Seen this way,the answer is much clearer.Delivering that throwaway to customers buys time,but it does so only at the (75) of agony(极大痛苦)for the user,distraction for the builders while they do the redesign,and a bad reputation for the product that best redesign will find hard to live down.
Hence plan to throw one away;you will,anyhow.
71.()
A.almost
B.often
C.usually
D.barely
第2题
A.the connecting rod
B.large end bearing
C.the main bearing
D.the desig
第3题
A.AdministrativeDepartment
B.ProductionDepartment
C.PublicRelationsDepartment
D.Research﹠DevelopmentDepartment
E.Sales﹠MarketingDepartment
第4题
下面所列的工具中,不能用于数据库应用系统界面开发的工具是
A.Visual Basic
B.Delphi
C.Power Designer
D.Power Builder
第5题
The project is only__________ (theory)workable.
第6题
● The scope baseline/project charter is prepared by the:
A Project manager
B Project manager and project office
C Project manager, project office and functional team
D Project manager, project office, functional team and project sponsor
E Project manager, project sponsor and customer/user
第7题
● The project charter is a document designed to tell _____ exactly what the project entails.
A The project manager
B The project office
C The project team
D The project sponsor
E Anyone associated with the project
第8题
● The project life-cycle can be described as(72).
(72)
A.project concept, project planning, project execution, and project close-out
B.project planning, work authorization, and project reporting
C.project planning, project control, project definition, WBS development, and project termination
D.project concept, project execution, and project reporting
第9题
AThe project manager
BThe project office
CThe project team
DThe project sponsor
EAnyone associated with the project
第11题
A.Developing project charter
B.Developing project management plan
C.Analyzing project risks
D.Monitoring and controlling project