题目
● The project charter is prepared in which scope management process?
A Initiation
B Scope planning
C Scope Definition
D Scope change control
E Scope verification
第1题
The project charter is developed by:
A.senior management
B.the customer
C.the project manager
D.both A and C
E.None of the above.
第2题
● The project charter is a document designed to tell _____ exactly what the project entails.
A The project manager
B The project office
C The project team
D The project sponsor
E Anyone associated with the project
第3题
The scope baseline/project charter is prepared by the:
AProject manager
BProject manager and project office
CProject manager, project office and functional team
DProject manager, project office, functional team and project sponsor
EProject manager, project sponsor and customer/user
第4题
139 The project charter is a document designed to tell _____ exactly what the project entails.
A. The project manager
B. The project office
C. The project team
D. The project sponsor
E. Anyone associated with the project
第5题
10 The project charter is developed by:
A. senior management
B the customer
C. the project manager
D. both A and C
E. None of the above
第6题
92 The project charter is developed by:
A. senior management
B. the customer
C. the project manager
D. both A and C
E. None of the above
第7题
The project charter:
A.Expresses upper management commitment to the project.
B.Provides that authority by which the project will be run.
C.Establishes that organizational structure with the project.
D.Specifies overall objectives and timeframe. of the project.
E.All of the above.
第8题
The inputs of developing project management plan do not include(72). A.project charter B.stakeholder management strategy C.project scope statement D.outputs from planning processes
第9题
● The scope baseline/project charter is prepared by the:
A Project manager
B Project manager and project office
C Project manager, project office and functional team
D Project manager, project office, functional team and project sponsor
E Project manager, project sponsor and customer/user
第10题
第11题
21 The project charter is a document designed to tell _____ exactly what the project entails.
A. The project manager
B. The project office
C. The project team
D. The project sponsor
E. Anyone associated with the project