题目
4 Total Project Risk:
A. should not be calculated for small projects
B. is the probability of each project risk event times the sum of the consequences of individual project risk events which could occur during the project.
C. Is the cumulative sum of the probability of each individual project risk event times the consequences of occurrence of that risk event.
D. A and B
E. A and C
第1题
Total project risk can be defined as:
A the sum of the probabilities of project risks events times the sum of consequences of those risks
B the sum of the products of each project risk event times its consequences
C the sum of the consequences of all project risk events
D the sum of the probabilities of all project risk events
E 1 - the sum of the probabilities of all project risk events.
第2题
97 Total project risk can be defined as:
A. the sum of the probabilities of project risks events times the sum of consequences of those risks
B. the sum of the products of each project risk event times its consequences
C. the sum of the consequences of all project risk events
D. the sum of the probabilities of all project risk events
E. 1 - the sum of the probabilities of all project risk events
第3题
15 Total project risk can be defined as:
A. the sum of the probabilities of project risks events times the sum of consequences of those risks
B. the sum of the products of each project risk event times its consequences
C. the sum of the consequences of all project risk events
D. the sum of the probabilities of all project risk events
E. 1 - the sum of the probabilities of all project risk events
第4题
Giving a part of project work to a contractor is an example of:
A risk mitigation
B risk assignment
C risk delegation
D risk deflection
E risk assumption
第5题
Risk management allows the project manager and the project team not to(71). A.eliminate most risks during the planning phase of the project B.identify project risks C.identify impacts of various risks D.plan suitable responses
第6题
125 In Project Risk Management, Risk Response may include actions to:
A. reduce the probability of risk events
B. change the scope, budget, schedule or quality specifications of the project
C. reduce the consequences or severity of impacts of a potential risk event
D. A and C
E. All of the above
第7题
It is useful to conduct project risk assessment according to the project's
A charter
B statement of work
C Work Breakdown structure
D network
E budget
第8题
● Risk management allows the project manager and the project team not to(71).
(71)
A.eliminate most risks during the planning phase of the project
B.identify project risks
C.identify impacts of various risks
D.plan suitable responses
第9题
122 Total Project Risk:
A. should not be calculated for small projects
B. is the probability of each project risk event times the sum of the consequences of individual project risk events which could occur during the project.
C. Is the cumulative sum of the probability of each individual project risk event times the consequences of occurrence of that risk event.
D. A and B
E. A and C
为了保护您的账号安全,请在“赏学吧”公众号进行验证,点击“官网服务”-“账号验证”后输入验证码“”完成验证,验证成功后方可继续查看答案!