题目
The schedule risk is the _____ .
A the accumulated "expected' durations which maintain project completion.
B Critical Path adjusted by "high-risk" activity float.
C highest risk path that maintains quality.
D Critical Path when calculated with "most likely" duration.
E highest risk path that contributes the most risk toward the project completion.
第1题
Which of the following does not contribute to increased Schedule Risk?
A labor shortage
B contractor claims
C lack of access
D sponsor scope changes
E all may increase schedule risk
第2题
125 Which of the following does not contribute to increased Schedule Risk?
A. labor shortage
B. contractor claims
C. lack of access
D. sponsor scope changes
E. all may increase schedule risk
第3题
194 The schedule risk is the _____ .
A. the accumulated "expected' durations which maintain project completion.
B. Critical Path adjusted by "high-risk" activity float.
C. highest risk path that maintains quality.
D. Critical Path when calculated with "most likely" duration.
E. highest risk path that contributes the most risk toward the project completion
第4题
7 Which of the following does not contribute to increased Schedule Risk?
A. labor shortage
B. contractor claims
C. lack of access
D. sponsor scope changes
E. all may increase schedule risk
第5题
A.Quantitative Risk Analysis
B.Qualitative Risk Analysis
C.Enterprise Environmental Factors
D.Risk Management Plan
第6题
The Work Breakdown Structure (WBS) is the basis for communicating:
A.Project scope, cost control, schedule, quality
B.Project objectives, dependencies, plan, cost control
C.Project scope, schedule, staffing, cost control
D.Project scope, quality, schedule, dependencies
E.Project budget, schedule, risk factors, work assignments.
第7题
The most crucial time for project risk assessment is (75) .
A.when a problem surfaces
B.during the planning phase
C.during the close-out phase
D.after the project schedule has been published
第8题
The most crucial time for project risk assessment is ().
A.when a problem surfaces
B.during the planning phase
C.during the close-out phase
D.after the project schedule has been published
第9题
In Project Risk Management, Risk Response may include actions to:
A reduce the probability of risk events
B change the scope, budget, schedule or quality specifications of the project
C reduce the consequences or severity of impacts of a potential risk event
D A and C
E All of the above.