题目
The budgeted cost of the work performed (BCWP) for a task that has just been completed can be calculated by:
A . Multiplying the actual hours worked on the project by the budgeted labor rate.
B . Multiplying the budgeted hours to complete the task by the budgeted labor rate.
C . Dividing the actual hours required to complete the task by the budgeted labor rate.
D . Cannot be determined.
E . None of the above
第1题
The cost of a quality program should be budgeted at _____ of the total project.
A . 10-12%
B . 2-3 %
C . 6-8%
D . 3-5%
E . more than 15 %
第2题
192 The cost of a quality program should be budgeted at _____ of the total project.
A. 10-12%
B. 2-3 %
C. 6-8%
D. 3-5%
E. more than 15 %
第3题
110 The cost of a quality program should be budgeted at _____ of the total project.
A. 10-12%
B. 2-3 %
C. 6-8%
D. 3-5%
E. more than 15 %
第4题
A.Planned value
B.Earned value
C.Actual cost
D.Cost variance
第5题
159 The budgeted cost of the work performed (BCWP) for a task that has just been completed can be calculated by:
A. Multiplying the actual hours worked on the project by the budgeted labor rate.
B. Multiplying the budgeted hours to complete the task by the budgeted labor rate.
C. Dividing the actual hours required to complete the task by the budgeted labor rate.
D. Cannot be determined.
E. None of the above
第6题
Using the cumulative cost curve in the special window, height B represents
A.actual cost to date
B.total budgeted costs for the project
C.planned cost for month
D.cost variance
E.earned value
第7题
A.How much have you budgeted for the training?
B.How long will the training last?
C.How much has the training cost?
第8题
A.Cost Variance B.Schedule Variance C.Earned Value D.Cost Performed Index
第9题
A.Planned value
B.Actual cost
C.Earned value
D.Cost variance