● The critical path in a schedule network is the path that:
A Takes the longest time to complete
B Must be done before any other tasks
C Allows some flexibility in scheduling a start time.
D Is not affected by schedule slippage
E All of the above.
第2题
The critical path in a schedule network is the path that:
A.Takes the longest time to complete
B.Must be done before any other tasks
C.Allows some flexibility in scheduling a start time.
D.Is not affected by schedule slippage
E.All of the above.
第3题
Word has come __________ some guests from canada will visit our school.
A.what
B.that
C.whether
D.when
第5题
She wanted to serve some coffee to her guests; however, _________.
A.she hadn't many sugar
B.there was not a great amount of the sugar
C.she did not have much sugar
D.she was lacking in amount of the Sugar.
第6题
Some of the guests ______ to the party were from other cities.
A.to invite
B.invited
C.being invited
D.had been invited
第7题
A.A. having not considered
B.B. not having considered
C.C. having not been considering
D.D. not considering
第8题
A、most guests pay little attention to them.
B、most travelers are willing to ask for help from a staff.
C、some guests may still want to be greeted when they arrive.
D、most guests are difficult in using them.
第10题
Ann's first piece of advice is that Mary should______.
A.get the food ready before the guests arrive
B.keep the guests away from the kitchen
C.spend some time with the guests
D.accept the guests' offer to help
为了保护您的账号安全,请在“赏学吧”公众号进行验证,点击“官网服务”-“账号验证”后输入验证码“”完成验证,验证成功后方可继续查看答案!