题目
● The Estimate Activity Resource process is closely coordinated with the (73)process.
(73)
A. Estimate Costs
B. Sequence Activities
C. Plan Communications
D. Conduct Procurements
第1题
The Estimate Activity Resource process is closely coordinated with the(73)process.
A.Estimate Costs
B.Sequence Activities
C.Plan Communications
D.Conduct Procurements
第2题
The Estimate Activity Resource process is closely coordinated with the(73) process.
A.Estimate Costs
B.Sequence Activities
C.Plan Communications
D.Conduct Procurements
第3题
The Estimate Activity Resource process is closely coordinated with the(73)process.
A.Estimate Costs
B.Sequence Activities
C.Plan Communications
D.Conduct Procurements
第4题
The Estimate Activity Resource process is closely coordinated with the(73) process.
A.Estimate Costs
B.Sequence Activities
C.Plan Communications
D.Conduct Procurements
第5题
The Estimate Activity Resource process is closely coordinated with the (73)process.
(73)
A. Estimate Costs
B. Sequence Activities
C. Plan Communications
D. Conduct Procurements
第6题
The process of(72)schedule activity durations uses information on schedule activity scope of work,required resource types,estimated resource quantities,and resource calendars with resource availabilities.
A.estimating
B.defining
C.planning
D.sequencing
第7题
The process of(17)schedule activity durations uses information on schedule activity scope of work, required resource types' estimated resource quantities, and resource calendars with resource availabilities.
A.estimating
B.defining
C.planning
D.sequencing
第8题
The process of (74) schedule activity durations uses information on schedule activity scope of work, required resource types, estimated resource quantities, and resource calendars with resource availabilities.
A.defining
B.estimating
C.planning
D.sequencing
第9题
A.estimating
B.defining
C.planning
D.sequencing
第10题
A.estimating
B.defining
C.planning
D.sequencing