题目
A.Benefitcontribution
B.Expertjudgment
C.Scoringmodels
D.Flowcharting
第1题
Selection criteria for project selection include:
A.cost versus benefit
B.risk
C.contribution towards organizational goals
D.rate of return
E.All of the above.
第2题
(74)
A.Benefit contribution
B.Expert judgment
C.Scoring models
D.Flowcharting
第3题
● The appointment or selection of a project sponsor is often based upon:
A The strategic importance of the project
B Who the customer is
C Whether the organization is project or non-project-driven
D The profitability of the project
E All of the above
第4题
● Selection criteria for project selection include:
A cost versus benefit
B risk
C contribution towards organizational goals
D rate of return
E All of the above.
第5题
The appointment or selection of a project sponsor is often based upon:
AThe strategic importance of the project
BWho the customer is
CWhether the organization is project or non-project-driven
DThe profitability of the project
EAll of the above
第6题
A.Benefit contribution
B.Expert judgment
C.Scoring models
D.Flowcharting
第7题
32 The appointment or selection of a project sponsor is often based upon:
A. The strategic importance of the project
B. Who the customer is
C. Whether the organization is project or non-project-driven
D. The profitability of the project
E. All of the above
第8题
123 Selection criteria for project selection include:
A. cost versus benefit
B. risk
C. contribution towards organizational goals
D. rate of return
E. All of the above
第9题
● The identification, definition, and selection of the project objectives as well as the best approach to achieving the project objectives are indentified in the _____ phase of the project but first documented in the project _____.
A Conceptual, charter/baseline.
B Conceptual, master schedule.
C Development, charter/baseline.
D Development, master schedule.
E Development, masterplan.
第10题
12 The identification, definition, and selection of the project objectives as well as the best approach to achieving the project objectives are indentified in the _____ phase of the project but first documented in the project _____.
A. Conceptual, charter/baseline.
B. Conceptual, master schedule.
C. Development, charter/baseline.
D. Development, master schedule.
E. Development, masterplan
为了保护您的账号安全,请在“赏学吧”公众号进行验证,点击“官网服务”-“账号验证”后输入验证码“”完成验证,验证成功后方可继续查看答案!