题目
(74)
A.Benefit contribution
B.Expert judgment
C.Scoring models
D.Flowcharting
第1题
Selection criteria for project selection include:
A.cost versus benefit
B.risk
C.contribution towards organizational goals
D.rate of return
E.All of the above.
第2题
● The appointment or selection of a project sponsor is often based upon:
A The strategic importance of the project
B Who the customer is
C Whether the organization is project or non-project-driven
D The profitability of the project
E All of the above
第3题
● Selection criteria for project selection include:
A cost versus benefit
B risk
C contribution towards organizational goals
D rate of return
E All of the above.
第4题
The appointment or selection of a project sponsor is often based upon:
AThe strategic importance of the project
BWho the customer is
CWhether the organization is project or non-project-driven
DThe profitability of the project
EAll of the above
第5题
A.Benefit contribution
B.Expert judgment
C.Scoring models
D.Flowcharting
第6题
32 The appointment or selection of a project sponsor is often based upon:
A. The strategic importance of the project
B. Who the customer is
C. Whether the organization is project or non-project-driven
D. The profitability of the project
E. All of the above
第7题
● The identification, definition, and selection of the project objectives as well as the best approach to achieving the project objectives are indentified in the _____ phase of the project but first documented in the project _____.
A Conceptual, charter/baseline.
B Conceptual, master schedule.
C Development, charter/baseline.
D Development, master schedule.
E Development, masterplan.
第8题
123 Selection criteria for project selection include:
A. cost versus benefit
B. risk
C. contribution towards organizational goals
D. rate of return
E. All of the above
第9题
A.Benefitcontribution
B.Expertjudgment
C.Scoringmodels
D.Flowcharting
第10题
12 The identification, definition, and selection of the project objectives as well as the best approach to achieving the project objectives are indentified in the _____ phase of the project but first documented in the project _____.
A. Conceptual, charter/baseline.
B. Conceptual, master schedule.
C. Development, charter/baseline.
D. Development, master schedule.
E. Development, masterplan
为了保护您的账号安全,请在“赏学吧”公众号进行验证,点击“官网服务”-“账号验证”后输入验证码“”完成验证,验证成功后方可继续查看答案!