The project charter is developed by:
A.senior management
B.the customer
C.the project manager
D.both A and C
E.None of the above.
第1题
● The project charter is a document designed to tell _____ exactly what the project entails.
A The project manager
B The project office
C The project team
D The project sponsor
E Anyone associated with the project
第2题
The scope baseline/project charter is prepared by the:
AProject manager
BProject manager and project office
CProject manager, project office and functional team
DProject manager, project office, functional team and project sponsor
EProject manager, project sponsor and customer/user
第3题
139 The project charter is a document designed to tell _____ exactly what the project entails.
A. The project manager
B. The project office
C. The project team
D. The project sponsor
E. Anyone associated with the project
第4题
10 The project charter is developed by:
A. senior management
B the customer
C. the project manager
D. both A and C
E. None of the above
第5题
The project charter:
A.Expresses upper management commitment to the project.
B.Provides that authority by which the project will be run.
C.Establishes that organizational structure with the project.
D.Specifies overall objectives and timeframe. of the project.
E.All of the above.
第6题
92 The project charter is developed by:
A. senior management
B. the customer
C. the project manager
D. both A and C
E. None of the above
第7题
The inputs of developing project management plan do not include(72). A.project charter B.stakeholder management strategy C.project scope statement D.outputs from planning processes
第8题
● The scope baseline/project charter is prepared by the:
A Project manager
B Project manager and project office
C Project manager, project office and functional team
D Project manager, project office, functional team and project sponsor
E Project manager, project sponsor and customer/user
第9题
第10题
21 The project charter is a document designed to tell _____ exactly what the project entails.
A. The project manager
B. The project office
C. The project team
D. The project sponsor
E. Anyone associated with the project