在下面的项目活动图7-3中,关键路径的时长为(10)周。

A.27

B.28

C.29

D.30

参考答案
正确答案:B
解析:参考(1)题和(7)、(8)题的分析。通过计算,可知关键路径为B→F→K→0,即28周。
您可能感兴趣的试题
  • The process of translating the qualitymangement plan into executable quality activities that incorporate theorganization's quality policies into the project.

    A.Manage quality

    B.Quality audit

    C.Quality metrics

    D.Quality improvement

  • Estimate activity durations is the processof estimating the number of work periods to complete indivities with estimatedresources . the tools and technques is not including().

    A.expert judgment

    B.analogous estimating

    C.requiremen tstraceability matrix

    D.three-point estimating

  • Is a decentralized, distributed and public digital ledger that is used to record transactions across many computers so that the record cannot be alterred retroactively without the alteration of all subsequent blocks and the collusion ?of the network().

    A.Cloud service

    B.Blockchain

    C.Internet of things

    D.Artificial intellingence

  • Is the technology that appears to emulate human performancetypicaliy by learning,coming to its own conclusions, appearing to understandcomplex content, engaging in natural dialogs with people, enhancing humancognittive performance (also known as cognittive computing) or replacing peopleon execution ofnonroutine tasks().

    A.Cloud service

    B.Blockchain

    C.Internet of things

    D.Artificial intellingence