题目
(74)A.the project is ahead of its planned schedule
B.less work was completed than was planned
C.the cost overrun for work completed
D.the cost under-run of performance to date
第1题
The ability to achieve cost savings is inversely proportional to _____.
A.the earned value achieved to date
B.the estimated costs to complete
C.empowerment to the P.M.
D.productivity
E.None of the above.
第2题
A、Schedule varlance (SV)
B、Cost varlance (CV)
C、Actual cost (AC)
D、Earned value (EV)
第3题
130 The ability to achieve cost savings is inversely proportional to _____.
A. the earned value achieved to date
B. the estimated costs to complete
C. empowerment to the P.M.
D. productivity
E. None of the above
第4题
24 A comparison of completion status to baseline is referred to as _____.
A. Earned value measurement.
B. Percent complete.
C. ACWP.
D. BCWS
E. None of above
第5题
48 The ability to achieve cost savings is inversely proportional to _____.
A. the earned value achieved to date
B. the estimated costs to complete
C. empowerment to the P.M.
D. productivity
E. None of the above
第6题
项目成本控制的一种重要方法是挣值分析法,挣值管理(Earned Value Management)是综合了项目范围、进度计划和资源、测量项目绩效的一种方法,如下图,当出现(53)时,说明工程滞后。
A.SV>0
B.SV<0
C.CV>0
D.CV<0
第7题
A.cost variance
B.planned cost
C.planned cost
D.actual cost
第8题
A . Trend line.
B . Trend analysis.
C . S curve.
D . Percent completion report.
E . Earned value report.
第9题
46 Graphical displays of accumulated cost and labor hours, plotted as a function of time, are called: A. Variance reports
B. S curves
C. Trend analysis
D. Earned value reporting
E. Baseline control
第10题