● The completion and approval of one or more () characterizes a project phase.()A.deliverables B.products C.projects D.programs
第1题
A beneficial completion
B substantial completion
C project completion
D contract closeout
E final completion
第2题
58 Which of the following terms refers to the situation where the work is being used for the purpose intended and so certified:
A. beneficial completion
B. substantial completion
C. project completion
D. contract closeout
E. final completion
第3题
A comparison of completion status to baseline is referred to as _____.
A.Earned value measurement.
B.Percent complete.
C.ACWP.
D.BCWS
E.None of above.
第4题
We are of course() that the period for completion of your project has already been exceeded .
A. know
B. to know
C. aware
D. sure
第6题
PDM includes four types of dependencies or precedence relation ships:(73)The completion of the successor activity depends upon the initiation of the predecessor activity.
A.Finish-to-Start
B.Finish-to-Finish
C.Start-to-Start
D.Start-to-Finish
第7题
105 Upon completion of 75% of the project, the original schedules and cost estimates that were submitted at the inception of the project are referred to as the:
A. Baseline costs
B. Budgeted costs.
C. Estimates upon completion costs
D. Scheduled costs
E. None of the above
第8题
23 Upon completion of 75% of the project, the original schedules and cost estimates that were submitted at the inception of the project are referred to as the:
A. Baseline costs
B Budgeted costs.
C. Estimates upon completion costs
D. Scheduled costs
E. None of the above