试题(71)~(75)The analysis phase answers the questions of who will use the system, what the

试题(71)~(75)

The analysis phase answers the questions of who will use the system, what the system will do, and where and when it will be used. During this phase, the project team investigates ny current system,identifies (71) , and develops a concept for the new system. This phase as three steps: first, (72) is developed to guide the project team's efforts. It usually ncludes an analysis of the current system and its problems, and the ways to design a new ystem. The next step is (73) The analysis ofthis information - in conjunction withinput rom the project sponsor and many other people - leads to the development of a concept for a ew system. The system concept is then used as a basis to develop a set ofbusiness analysis odels that describes how the business will operate if the new system were developed. The set of models typically includes models that represent the (74) necessary to support the nderlying business process. Last, the analyses, system concepts, and models are combined nto a document called the (75), which is presented to the project sponsor and other key ecision makers that decide whether the project should continue to move forward.

(71) A. improvementopportunities

B. logicalmodel

C. systemrequirements

D. systemarchitecture

(72) A. a user manual

B. an analysis strategy

C. an analysis use case

D. a design user case

(73) A. project scope definition

B. prob,lems analysis

C. decisionanalysis

D. requirementsgathering

(74) A. dataandprocesses

B. systeminfrastructures

C. externalagents

D. systemsoftware

(75) A. requirementsstatement

B. designspecification

C. systemproposal

D. project charter


  参考答案

正确答案:A,B,D,A,C

参考译文
分析阶段回答谁将使用该系统、系统能做什么及系统在何时何地使用的问题。在该阶段,项目组调研当前系统、识别改进机会并开发出一个新系统的概念。这个阶段分为三个步骤:首先,开发一个分析策略来指导项目组工作。这些分析策略通常包括了当前系统及其问题的分析和设计新系统的方法。下一步是需求收集。对这些信息(汇同系统发起人和很多其他人员的输入)的分析会导致开发出一个新系统的概念。系统概念作为开发一组业务分析模型的基础,这些模型描述了新系统开发完成后企业如何运作。这组模型通常包含那些表示数据和过程的模型,这些数据和过程是支持底层业务过程所必需的。最后,这些分析、系统概念和模型合并到一个称为系统建议书的文档中,将被提交给项目组发起人和其他决定项目是否继续执行的主要决策人员。
参考答案
(71)A
(72)B
(73)D
(74)A
(75)C

相关题目:

● 在CPM网络中,A为B的紧前活动,则表示()。()A.活动A完工后B马上就要开始 B.活动A完成是活动B开始的充分条件C.活动B在活动A完成后才有可能开始 D.活动A和B同为关键路径或非关键路径
● 某项任务的乐观工期为3天,最可能工期为6天,悲观工期为9天,此任务的预期工期为()天。()A.3 B.6 C.9 D.6.5
● 在执行计划时你发现了一个错误,这将导致你无法在指定日期到达里程碑,你最应该做的是()。() A. 开发备选方案来实现里程碑日期 B. 变更里程碑日期 C. 从项目状态报告中删除任何关于里程碑日期的讨论 D. 教育团队认识按时到达里程碑的必要性