题目
123 The scope baseline/project charter is prepared by the:
A. Project manager
B. Project manager and project office
C. Project manager, project office and functional team
D. Project manager, project office, functional team and project sponsor
E. Project manager, project sponsor and customer/user
第1题
The scope management provides:
A.A basis for future decisions about the project.
B.A baseline to accomplish verification measures.
C.A baseline to evaluate potential scope changes.
D.All of the above.
E.B and C only.
第2题
88 The scope statement provides
A. A basis for future decisions about a project.
B. A baseline to accomplish verification measures.
C. A baseline to evaluate potential scope changes.
D. All of the above
E. B and C only
第3题
123 The scope of a project can be expected to change if:
A. The project manager must provide cost estimates without having a design concept B. Oversimplification (underestimating) of the nature of the work occurs
C. The project manager is assigned after the project is defined, and the cost and schedule are approved D. A clear objective is not provided
E. All of the above are possible based upon the situation
第4题
Dr. Myers and other researchers hold that ________.
[A] people should look for a baseline that can’t work for a longer time
[B] fisheries should keep the yield below 50% of the biomass
[C] the ocean biomass should restored its original level
[D] people should adjust the fishing baseline to changing situation
第7题
A.Request Scope
B.Response Scope
C.Out Scope
D.Writer Scope