题目
Cost and schedule data are usually integrated because:
A.optimized project cash flow can affect financial requirements
B.they provide MIS with an integrated system to produce reports
C.they control escalation allowances
D.they account for omissions in the definitive estimate
E.they predict future performance
第1题
What is the relative priority of project Cost, Schedule and Quality?
A . 1)Cost - 2)Schedule - 3)Quality
B . 1)Quality - 2)Schedule - 3)Cost
C . 1)Quality - 2)Cost - 3)Schedule
D . 1)Schedule - 2)Quality - 3)Cost
E . All are of equal priority
第2题
第3题
12 What is the relative priority of project Cost, Schedule and Quality?
A. 1)Cost - 2)Schedule - 3)Quality
B. 1)Quality - 2)Schedule - 3)Cost
C. 1)Quality - 2)Cost - 3)Schedule
D. 1)Schedule - 2)Quality - 3)Cost
E. All are of equal priority
第4题
The Work Breakdown Structure (WBS) is the basis for communicating:
A.Project scope, cost control, schedule, quality
B.Project objectives, dependencies, plan, cost control
C.Project scope, schedule, staffing, cost control
D.Project scope, quality, schedule, dependencies
E.Project budget, schedule, risk factors, work assignments.
第5题
Estimating schedule activity costs involves developing an (74) of the cost of the resources needed to complete each schedule activity.
A.accuracy
B.approximation
C.specification
D.summary
第6题
A negative cost variance and positive schedule variance means:
A The project is under budget and ahead of schedule
B The project is over budget and behind schedule
C The project is over budget and ahead of schedule
D The project will be overrun but ahead of schedule at completion
第7题
● Project trade-offs vary between
A risk, cost and schedule.
B direct cost, indirect cost, and resource availability
C quality, schedule and time
D cost, quality and schedule
E contract terms, scope and budget
第8题
57 Which of the following are types of status reports?
A. document, variance, trend and exception
B. cost, trend, schedule and acquisition
C. cost, schedule, technical performance
D. analysis, cost, performance and schedule
E. All of the above.
第9题
Project trade-offs vary between
A . risk, cost and schedule.
B . direct cost, indirect cost, and resource availability
C . quality, schedule and time
D . cost, quality and schedule
E . contract terms, scope and budget
第10题
2 The Work Breakdown Structure (WBS) is the basis for communicating:
A. Project scope, cost control, schedule, quality
B. Project objectives, dependencies, plan, cost control
C. Project scope, schedule, staffing, cost control
D. Project scope, quality, schedule, dependencies
E. Project budget, schedule, risk factors, work assignments